01 . Secure all Planting materials, soil sources and Growing media.
Monday, June 8, 2020
2. Check difficulties of material delivery to site and within the site/ Temporary store area ◦ Id works finished area ◦ Access restriction area
Sunday, June 7, 2020
3. Check all drain points in site with the drawings and finishing levels of ID works
Add caption
Saturday, June 6, 2020
4. Take photos of all bottom drain points for future maintenance.
Friday, June 5, 2020
5. Start Drain-cell and geotextile works
Thursday, June 4, 2020
6. Sand filling
Wednesday, June 3, 2020
8.Top soil works and basic Land preparation
7. Take photos of all planting beds for future maintenance(Electrical wiring)
Tuesday, June 2, 2020
9. Irrigation system(sprinkler/Drippers or taps)
Monday, June 1, 2020
10. Installing big trees and palms.
11. Layering Growing media and final Land preparation.